Inspection report
You record the inspection report in the mobile app at the stand. It needs a network. Everyone with the right to inspections & defects on the object may record: agency and technical lead in the whole event, sector lead and contractor in their own sectors.
At the stand “Inspection report”, then “Contractor reports ready” (contractor inspection, choose contractor; you can choose the contractors taking part in the event) or “Start authority inspection”.
A contractor reports ready itself with its own access: at the stand “Inspection report” → “… report ready”. This starts the contractor inspection with its trade’s checklist, and the technical lead gets an open item at the stand. The contractor cannot inspect or complete; it only sees the report. From the inspection round, “Start inspection” opens the stand’s inspections.
Fill in
Section titled “Fill in”- Participants: who inspects, who records, the contractor and others present. The name fields suggest people of the event; picking an exact name links the person, otherwise it stays free text. The authority is only recorded as present, never as a person.
- Checklist: for a contractor inspection from the contractor’s template; “Add check item” for more. Tick each item or leave it open, plus note, photo or condition until (deadline, only on open items).
- Photos of the inspection; they are scaled down on the phone. A photo still above 4 MB is not sent.
- Signatures: contractor and technical lead with a finger. Only then can you complete it. Above them “Save location with the signature (only if the device allows it)” (off): when on, every signature drawn afterwards stores the device’s location if the browser and device allow it. Signing never waits for it, the PDF does not show the location; it is deleted after the retention period like the names.
The result follows from the checklist: Accepted, Accepted with conditions or Not accepted. The button shows it, e.g. “Accepted with 1 condition”.
Complete
Section titled “Complete”Completing stores the report as a PDF in the file and sends it to the contractor and the customer. The delivery shows per recipient (sent, not sent, no e-mail address); “Send again” only applies to those not sent. For authority and contractor inspections, completing sets the stand to Inspection OK, unless the result is Not accepted. A completed report can no longer be changed. Everything appears in the log.
If the stand is accepted (also with conditions), completing sets it to “Inspection OK”, but only when all defects are fixed and the stand has arrived. Otherwise the report is saved anyway, the status stays, and the app tells you why. Then set “Inspection OK” at the stand once the defects are fixed.
Inspection after teardown
Section titled “Inspection after teardown”After teardown you inspect every stand together with the organizer and city cleaning. At the stand “Inspection report” → “Start inspection after teardown”. The button is only active from the event’s deadline “Inspection after teardown” (under deadlines, Theatrium: Mon 00:00); above it you see from when. Once the clock reaches the deadline, the button becomes active without a reload. Without that deadline it cannot be started; if the phone’s clock runs ahead, the start says the deadline has not been reached yet.
- Participants: you inspect; organizer and city cleaning (as authority) are present, plus the stand operator and who records. Whoever is not there: clear the name.
- Checklist from the template “Inspection after teardown”. An open item is a defect (finding); instead of a condition you choose the entry from the defect catalog (or none, as free text), plus note and photo.
- Signatures (stand operator, inspector) are optional.
The result is “Teardown OK” (all ticked) or “Teardown with defects”. Teardown OK moves the stand from accepted to teardown OK; if the stand is not accepted (e.g. an open defect), teardown OK cannot be completed. On completion every finding becomes an open defect of the stand with photo and catalog entry – the basis for deductions from the deposit. The stand’s status stays. Findings do not escalate and do not appear on the TV as defects past deadline. The completed protocol shows the catalog entry at each finding. Teardown OK is the final status: no status button and no new defect changes it any more, only correct status. PDF and delivery as above (to stand operator and customer). Teardown OK cannot be completed while a defect (also a finding) is open.
Teardown OK and findings without a network
Section titled “Teardown OK and findings without a network”From the deadline the stand shows the section “Teardown” – also offline:
- “Teardown OK” sets the stand to teardown OK. The button is only active if the stand is accepted and no defect is open; otherwise the reason shows below it.
- “Report finding” opens the form “Finding after teardown”: entry from the defect catalog (or “+ Custom”), photos (scaled like other photos), note. No deadline, trade or SMS. The finding shows right away as an open defect (“waiting”), the status stays.
When sent, the server creates exactly once per Teardown OK or finding report a completed inspection after teardown (result Teardown OK or Teardown with defects, you as “records”), with the PDF filed; findings become defects of that inspection and count for the deposit like online. There are no signatures; the mails to stand operator and customer go out via “Send again” in the protocol. If the rules no longer hold when sent, nothing is applied (see Conflicts).
Templates
Section titled “Templates”The agency maintains the checklists per contractor and for the inspection after teardown per event under “Catalogs” → “Inspection templates” (catalog); choose “Inspection after teardown” under “Checklist for”. There are no default items for the inspection after teardown.