Milestones are points in time during setup that other work waits for, for example “Towers up” (banners can go on the towers afterwards) or “Stage roof goes up” (the stage banners must hang before). Instead of asking for the time by phone, the responsible trade contractor enters it and reports when it is done.

Role Sees May
Agency all milestones create, edit, delete, enter the time, report “reached”
Responsible trade contractor own milestones enter and change the time, report and undo “reached”
Sector lead, technical lead, customer all milestones read
Other trade contractors, stand operators – –

The trade contractor works in its own login (contact person and logged-in crew). QR accesses have no milestones.

  1. Open “Milestones” in the event.
  2. Under “Add milestone” enter the title, choose the responsible trade contractor and optionally an object (e.g. the stage). The planned time may stay empty; the trade contractor then enters it.
  3. “Add milestone”.

Only trade contractors taking part in the event can be chosen (see Accesses and organizations). “Edit” on a milestone changes everything or deletes it. This works directly only for milestones you created; otherwise it becomes a counter-proposal to the person who created it.

Cancelled objects are no longer offered. One already selected stays when saving; the milestone stays and shows “Cancelled”.

Under “Edit” (or when creating) choose under “Notify when reached” the teams and trade contractors of the event that should learn that the milestone is reached, for example the banner team for “Towers up”. With “Send push” they also get a push notification on their phone.

When the milestone is reported reached, a broadcast goes out automatically to exactly these recipients: always as a notice in the app, with the box also by push, never by SMS or email. Each report sends exactly one broadcast; “Undo reached” sends nothing, reporting again sends a new one. Without recipients nothing goes out. The line below the milestone shows who is notified.

Enter the time and report “reached” (trade contractor)

Section titled “Enter the time and report “reached” (trade contractor)”
  • Planned time: enter date and time (Europe/Berlin), “Save time”. Saving it empty removes the time.
  • “Report reached”: the milestone is reached; the time and the person are stored.
  • “Undo reached”: if it was reported too early.

When the trade contractor changes the planned time, the agency gets an open item (to-do, high priority, internal) with the old and the new time. When the agency changes the time itself, no item is created.

Symbol Meaning
Empty, faint ring No time: not planned yet
Dashed ring Planned: time set, still open
Full Reached, with time and person

The list is sorted by planned time; milestones without a time come last. The symbols are explained under status symbols.

Milestones with a planned time show at the very top of the timeline in the group “Milestones”, each in its own row with title, time and status symbol and a diamond at the planned time; filled means reached. The group can be collapsed. The area and sector filters do not apply to this group.

All readable milestones also show in the stand list as a group and on the board as the first column. A click there, or on the title or diamond in the timeline, opens this page at that milestone: it is highlighted, and whoever may edit it sees the “Edit” form already open. The link (…/milestones#milestone-…) can be shared.

Tasks can wait for a milestone (startable once it is reached), follow its planned time with their start, or have to be done before it. When the trade contractor enters a new time, coupled tasks move with it.

Every change is in the log. When a follow-up event is created, title, trade contractor, the trade contractors as recipients and “Send push” are copied; planned time, “reached” and object are not. Teams only exist in the follow-up event once you create them: a team from the same team template becomes a recipient again.