Water plan
The water plan shows all booked water connections (½ inch) of an event: on the site plan and as a list by sector. The water contractor sees where to lay connections, without prices or the exhibitors’ contact data.
Where the connections come from
Section titled “Where the connections come from”The connections come from the objects’ water requirements, in every time window (setup, operation, changeover, teardown): from the Excel import, from confirming a stand request (checkbox “Water connection ½ inch” in the Power step) or from the object detail. They can only be added and changed there, not in the water plan. A requirement without a quantity counts as one connection.
Who may do what
Section titled “Who may do what”| Role | Sees | May |
|---|---|---|
| Agency | all connections | read and export, own water plan |
| Water contractor | all connections; if the person is restricted to sectors, only those of these sectors | read and export, own water plan |
| Sector lead, technical lead, customer | customer all connections; sector lead and technical lead those in their sectors and those without a sector | read and export |
| Other contractors | only connections of their own objects | read and export |
| Exhibitor | – | – |
Water tapping points and distributors are not part of this version. Prices, finances and contact data appear neither on the page nor in the export.
Page header and plan
Section titled “Page header and plan”The header “Booked water connections” shows the number of connections, stands and stands with no position on the plan.
On the site plan, every stand with a water connection is a dot. Below the plan you see which site plan version applies and how many stands have no position yet. Without a site plan the list still applies.
Own water plan
Section titled “Own water plan”Without an own plan the water plan shows the site plan. If the contractor has a drawing of its own (e.g. a water overview), import it in the “Plan” section on the right: “Import own plan”, file (PDF or DXF) and scale as for the site plan, plus the offset to the site plan. The agency and the water contractor may do this.
- Offset to site plan: only needed if the own plan shows a different section than the site plan. Then tick “Section differs from the site plan” and enter where the top-left corner of the own plan lies on the site plan, in metres (negative = left of or above it). Stands keep their positions on the site plan and appear shifted by the offset; nothing has to be placed again. The plan must have the same orientation as the site plan (not rotated). Without the tick the offset is 0 – right for trade plans extracted from the site plan with the same section.
- The site plan’s grid is drawn shifted along; grid cells stay those of the site plan.
- “New plan version” takes over the offset of the previous version; “Save offset” changes it.
- “Use site plan” deletes all versions of the own plan after a confirmation; the water plan shows the site plan again.
- The PDF export uses the own plan; stands outside of it are missing on the plan page but listed.
Site plan, security, TV view and the site plan excerpt of a broadcast always show the site plan. Import, offset and deletion are recorded in the log.
By sector
Section titled “By sector”On the right, the connections are listed by sector (stands without a sector last), each sector with its number of connections. Each row shows stand number, quantity, kind of time window and the time. Clicking a row highlights the stand on the plan.
Export and changes
Section titled “Export and changes”“Plan as PDF” creates the site plan with the stands and the list by sector. “List CSV” has one row per requirement with sector, stand, quantity, time window, from and to. Both contain only the connections you may see.
Every export is saved and noted in the log. The list “Since your last export (date)” then shows per stand what is new, what was removed, where the quantity changed and where the time window changed. Each contractor has its own last export; agency, sector lead, technical lead and customer share one.
Cancelled stands are left out of the page, the PDF, the list and the export baseline; since the last export they appear as “removed” in the change list. When the stand is reactivated everything is back.