The fence plan shows where which construction fences and crowd barriers go, and counts how many elements, gates, feet and clamps are needed in total. The fencing trade (contractor for fences and barriers) works in it directly.

Role Sees May
Agency the whole fence plan draw, edit, export, own fence plan
Fencing trade the whole fence plan draw, edit, export, own fence plan
Sector lead, technical lead, customer the whole fence plan read and export
Other trades, stand operators – –

The fencing trade is an organization with the trade “Fencing” (see Access and organizations). Fences belong to the event, not to a stand.

A segment is a straight run with a start and an end on the site plan or the own fence plan. Without either there is nothing to draw on.

  1. “+ Construction fence” or “+ Crowd barrier” places a 10 m horizontal segment in the middle of the visible plan.
  2. Drag the start and end points on the plan (mouse or finger; arrow keys 1 m, with Shift 0.1 m).
  3. Edit the segment on the right: Type, Gates, Elements (manual), Privacy screen and Note, then “Save”. “Delete” removes the segment.

A construction fence is a solid line, a crowd barrier a dashed one. Clicking an end point or a row of the list selects the segment.

Without an own plan the fence plan shows the site plan. If the contractor has a drawing of its own (e.g. a fence overview), import it in the “Plan” section on the right: “Import own plan”, file (PDF or DXF) and scale as for the site plan, plus the offset to the site plan. The agency and the fencing trade may do this.

  • Offset to site plan: only needed if the own plan shows a different section than the site plan. Then tick “Section differs from the site plan” and enter where the top-left corner of the own plan lies on the site plan, in metres (negative = left of or above it). Segments keep their positions on the site plan and appear shifted by the offset; nothing has to be drawn again. The plan must have the same orientation as the site plan (not rotated). Without the tick the offset is 0.
  • You draw and drag on the plan currently shown; switching plans changes no length or element count.
  • “New plan version” takes over the offset of the previous version; “Save offset” changes it.
  • “Use site plan” deletes all versions of the own plan after a confirmation; the fence plan shows the site plan again.
  • The PDF export uses the own plan; segments with an end outside of it are missing on the plan page but are in the totals and the list.

Import, offset and deletion are recorded in the log. An own fence plan is not taken over into a follow-up event.

Below the plan, the fence plan details for the fence contractor are kept once per event. They apply to the whole fence plan, not per segment or fence type.

  • Accessories: free text, e.g. fence blocks, rolls, emergency exit banners.
  • Setup and teardown: one period each with day and time; both ends or neither.
  • Storage area: area in m² and a note. “Confirmed” records who confirmed it and when. If you change or remove the m², the confirmation is dropped. Only the agency enters the storage area; the fence contractor can see it.
  • Contacts: name and phone, time range optional. Without a time range the entry is a general contact, with one it is the on-site contact during that time. General contacts come first, then by start. You can call the number directly; “Remove” asks first.

The agency and the fence contractor edit right on the page, everyone else with access to the fence plan reads. In archived events nothing can be changed. Every change appears in the log.

  • Element length: construction fence 3.50 m, crowd barrier 2.50 m.
  • Elements per segment = length ÷ element length, rounded up (at least 1). If the plan’s scale is off, enter the number under “Elements (manual)”; empty means: from the length again.
  • Gates are added as extra elements.
  • Privacy screen applies to all elements of the segment.
  • Construction fence only: feet = elements + 1 and clamps = elements − 1 per segment (gates not counted).

“Totals per type” lists per type the elements, the length, the elements with privacy screen, the gates and, for construction fences, feet and clamps. The header shows the number of segments and of all elements.

“Plan as PDF” renders the plan (own fence plan or site plan) with the numbered segments, then accessories, setup, teardown and storage area, the totals per type and the list of segments; contacts are in no export. “List CSV” has one row per segment (No., type, length, elements, with privacy screen, gates, feet, clamps, note) and one “Total” row per type.

Every export is stored and noted in the log. The list “Since your last export (date)” then shows per segment what is new, what was removed and which details changed. The fencing trade has its own last export; agency, sector lead, technical lead and customer share one.

When a follow-up event is created, the segments are copied with position and details, the exports and the fence plan details are not.